Socar & Turcas Aegean Refinery (STAR) Project Civil Works

760.000 m³ of various excavation works, 381.000 m³ of various filling works, 7353 reinforced concrete footings, 217.000 m³ of concrete works, 420.000 m2 of formworks, 20.340 tons of rebars, 940 tons of black or galvanized anchors, 480.000 m2 of field concrete pavements, 56.000 m2 of hot mix asphalt pavement, various isolation works, piping and wall works

Client
TSGI

Project Location
Aliağa – İzmir – Turkey

Start Date
27.11.2014

Completion Date
26.12.2018